Hello everyone and a very happy new year!
We wish to thank you all for your ongoing support and tell you a big sorry for all the delays we had so far.
2008 had been a very exciting year for us. With a lot of stepping stones. First we had the PayPal issue, then the banking problem with all those credit cards (and Amex is still troubling) and because of this we needed to reroute money from various other accounts to pay for the production... which caused delays, especially for the LCDs (though that issue is solved now, the last LCDs will ship soon, thank goodness).
And if that wasn't enough, we a bit trouble with the rechargeable battery, as it was pretty hard designing a battery with that high capacity that also FITS into the case. This delayed the case - but I'm happy to announce that the final battery is already being prototyped. As soon as we get it (which should be within the next week), the case design will be ready a few days later (we set the deadline for the case design to January 15th). Prototyping shouldn't take too long - and then it will only be a matter of a few weeks more until everything is ready for delivery.
So, while we're really sorry for those delays (believe me - we didn't expect THAT much problems - especially not from the banks... we couldn't have found a worse time to start this than that of a worldwide economical crisis.
However, we also got some good news for you AMEX guys: We know you didn't get your money back yet (we're having another meeting with the bank in the near future), however, we assure you that EVERYBODY WHO ORDERED AND PAID will get a Pandora, even if you didn't get the chance to reorder yet!
But, oh well, we did learn a lot - and now, after 2,5 years designing the system, the end of the trip is coming to an end. All thanks to you guys! Without your support, all this wouldn't have been possible!
Stay tuned for final prototype pics within this month!
So, here is a mini-roadmap:
* Case Design: January 15th
* Case Prototyping: approx. 1-2 weeks later
* Final production and delivery: approx. 2 - 4 weeks later
2009 will surely be the year of the Pandora.
http://www.openpandora.org/index.php
We wish to thank you all for your ongoing support and tell you a big sorry for all the delays we had so far.
2008 had been a very exciting year for us. With a lot of stepping stones. First we had the PayPal issue, then the banking problem with all those credit cards (and Amex is still troubling) and because of this we needed to reroute money from various other accounts to pay for the production... which caused delays, especially for the LCDs (though that issue is solved now, the last LCDs will ship soon, thank goodness).
And if that wasn't enough, we a bit trouble with the rechargeable battery, as it was pretty hard designing a battery with that high capacity that also FITS into the case. This delayed the case - but I'm happy to announce that the final battery is already being prototyped. As soon as we get it (which should be within the next week), the case design will be ready a few days later (we set the deadline for the case design to January 15th). Prototyping shouldn't take too long - and then it will only be a matter of a few weeks more until everything is ready for delivery.
So, while we're really sorry for those delays (believe me - we didn't expect THAT much problems - especially not from the banks... we couldn't have found a worse time to start this than that of a worldwide economical crisis.
However, we also got some good news for you AMEX guys: We know you didn't get your money back yet (we're having another meeting with the bank in the near future), however, we assure you that EVERYBODY WHO ORDERED AND PAID will get a Pandora, even if you didn't get the chance to reorder yet!
But, oh well, we did learn a lot - and now, after 2,5 years designing the system, the end of the trip is coming to an end. All thanks to you guys! Without your support, all this wouldn't have been possible!
Stay tuned for final prototype pics within this month!
So, here is a mini-roadmap:
* Case Design: January 15th
* Case Prototyping: approx. 1-2 weeks later
* Final production and delivery: approx. 2 - 4 weeks later
2009 will surely be the year of the Pandora.